Resource Availability View - Time Units

H

Hadi

Hello Experts,

I am using PWA 2003. Under Resources tab --> View Availability, why can't I
display the resource work hours by month. when I click on units under View
Options the only thing i see is days and weeks. is there a way around this?

Thank you,
 
M

Marc Soester [MVP]

Hi Hadi,

the only workaround is to use the OLAP Cubes or Portfolio Analyser. The
resource availabillity in PWA does only give you the options you mentioned.
You can achieve your request by building a Portfolio Analyser view.
hope this helps
 
H

Hadi

Marc,

Yes it does thank you. one question, can I stack the resources in the
portfolio analyzer view much like the resouce availability one?
 
M

Marc Soester [MVP]

Hi Hadi,

yes you can replicate the exact view in the portfolio Analyser.
 