Resource Availability

J

Joe Z

I am having a problem using the View Availability option in PWS. I created a
new calendar that has Saturday, March 11 as Working time and assigned it to a
specific project in MS Office Project 2003. It works fine in the plan and
tasks can be scheduled on the 11th.

When I go to the resource center and use the View Availability button for
the resources working on the 11th, the work time shows as all 0's.

Does anyone have advice on how to see the work that is scheduled?

Thank you in advance.
 
D

Dale Howard [MVP]

Joe Z --

Has the OLAP cube been rebuilt since you added the task calendar to the
project? If not, you won't see the work for March 11 until after the OLAP
cube rebuilds, since the resource availability information is processed at
the same time as the OLAP cube. Hope this helps..
 