J
Joe Z
I am having a problem using the View Availability option in PWS. I created a
new calendar that has Saturday, March 11 as Working time and assigned it to a
specific project in MS Office Project 2003. It works fine in the plan and
tasks can be scheduled on the 11th.
When I go to the resource center and use the View Availability button for
the resources working on the 11th, the work time shows as all 0's.
Does anyone have advice on how to see the work that is scheduled?
Thank you in advance.
new calendar that has Saturday, March 11 as Working time and assigned it to a
specific project in MS Office Project 2003. It works fine in the plan and
tasks can be scheduled on the 11th.
When I go to the resource center and use the View Availability button for
the resources working on the 11th, the work time shows as all 0's.
Does anyone have advice on how to see the work that is scheduled?
Thank you in advance.