I'm having an issue with one, just one, of my resources in displaying its
availability in PWA. When you click on Resources and bring up the Resource
Center, the resource I'm looking for is not in the list. However, when I
click on "View Resource assignments", it is in this list. Because it isn't in
the first list, I'm unable to view its availability.
This particular resource is an asset (piece of equipment). It is in the
resource pool and, since it is Project Server authenticated, I can even log
in to PWA as that resource.
One last thing, the OLAP cube is set to run each morning at 12:00 and PWA
indicates that it is running as scheduled. Any suggestions?
- Shane
availability in PWA. When you click on Resources and bring up the Resource
Center, the resource I'm looking for is not in the list. However, when I
click on "View Resource assignments", it is in this list. Because it isn't in
the first list, I'm unable to view its availability.
This particular resource is an asset (piece of equipment). It is in the
resource pool and, since it is Project Server authenticated, I can even log
in to PWA as that resource.
One last thing, the OLAP cube is set to run each morning at 12:00 and PWA
indicates that it is running as scheduled. Any suggestions?