A
Anne Thomas
When I change a resource's availability to work on a
project (let's say the resource cannot begin work on a
project until 2 weeks after the project has begun) and
then assign that resource to a task that is scheduled to
begin prior to the resource's availability, Microsoft
Project assigns the resource to the task as originally
scheduled and ignores the resource calendar. Scheduling
ignores resource calendar is not checked in the Task
Information dialog box.
Thanks,
Anne
project (let's say the resource cannot begin work on a
project until 2 weeks after the project has begun) and
then assign that resource to a task that is scheduled to
begin prior to the resource's availability, Microsoft
Project assigns the resource to the task as originally
scheduled and ignores the resource calendar. Scheduling
ignores resource calendar is not checked in the Task
Information dialog box.
Thanks,
Anne