Resource availability

K

Kimberly

We are using Project to schedule the departments machine hours to indicate
workload and availability. When a task is complete, marked as 100% complete,
how do you indicate the machine's new availability. It is not reducing the
scheduled the hours in the resource usage.
 
J

Jack Dahlgren

Set an "actual finish" which is equal to the date when the task completed.
The way you are doing it can result in having a finish date in the future
which is obviously not correct if the task is completed.

-Jack Dahlgren
 
J

Jim Aksel

In the resource usage view, try right clicking in the calendar side of the
view and select Remaining Availability. Is that what you wanted?
--
If this post was helpful, please consider rating it.

Jim

Visit http://project.mvps.org/ for FAQs and more information
about Microsoft Project
 
K

Kimberly

I set up a column with "actual finish"; entered the date when the task
completed; some tasks' duration changed to "zero" hours; others the duration
time either decreased and some even increased. My result is the resource has
more hours allocated to it than before.

Any suggestions?
 
J

Jack Dahlgren

In this case, you might want to go to the resource usage view and enter in
the actual work and remaining work.
Switch to resource view and then right click on the right hand side to add
additional fields that you can view.

-Jack Dahlgren
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top