You may be confusing terms.
Duration = the amount of time assigned as work hours between two dates.
Normally this is 40 hours/week over 5 days.
Work = The number of hours it takes to complete a task at an assumed
"production rate". I can work 6 hours on a task during an 8 hour day (I work
at 75% units)
Units% = the percentage of time a resource will donate to the task as a
percentage of their total availability on the resource sheet.
If Resource sheet availability is 100%, this is normally 40 hours/week. If
I assign this resource in the task at 75% the resource will work 30 hours on
the task.
Work = Units% x Duration.
This equation holds at all times. Assuming you have a work=25 hours task...
25 = 75% x Duration
Duration = 25/0.75 = 33.33333 work hours. This is 4.17 work days. There is
no way around this math.
MS Project allows you to specify which one to hold constant while the others
vary. This is the task type: Fixed Work, Fixed Duration, Fixed Units. The
default is fixed units.
If you want the task to be 25 hours over a fixed number of days, change the
task type to fixed duration, key 5 days for duration. Then assign the work
as 25 hours and let the Units% fall where it may.
Window/Split....
The bottom pane will allow you to assign resources, work, units%, task type,
etc.
--
If this post was helpful, please consider rating it.
Jim Aksel, MVP
Check out my blog for more information:
http://www.msprojectblog.com