resource availibility information

P

plan B

Hello,

In Project Web Access, I can access to see the
availibility of my resources. But this graph does not
correspond to the resource availibility declared in the
Enterprise projects.

When I check the availibility information within the
enterprise project (this time with the client Project
Professional)using the dialog box "Tools -> Assign
Resources -> Graphs", the information that is published
does not correspond to the information that is published
in PWA's resource availibility graph.

I have published the projects corectly and updated my OLAP Cube. There
are still diferences.

Thanks for your solution.
 
S

Scott McClure

Well, for one thing the two views use different units of measure. The Graph
in Pro is in Units while the PWA graph is in hours. Any help?
 
P

plan B

Unfortunately not. In my PWA Graph I have even tasks on sundays! In
Pro everything is correct. Something seems totaly messed. Maybe I have
to reinstall SQL and Analyse?
 
G

Gary Chefetz [MVP]

Plan B:

This is likely related to the combination of tracking method and task type.
For instance, if you're using weekly-buckets for hourly reporting on
Fixed-duration tasks, Project Web Access spreads the actual work from Sunday
through the end of the week.
 