Serge Locas
When we perform a save baseline when we are in a task view, the baseline work
and cost for the resources are not saved. When we baseline using a task
usage view, the baseline work and cost for the resources are saved, but the
rollup at the resource level does not work properly.
Any idea to keep the baseline data for the resources assigned to a project?
and cost for the resources are not saved. When we baseline using a task
usage view, the baseline work and cost for the resources are saved, but the
rollup at the resource level does not work properly.
Any idea to keep the baseline data for the resources assigned to a project?