D
Dots
Note: The below icon (which is viewable only on the Task Usage view at the
Task level) indicates that there is a mismatch between the task calendar and
the resource calendar; i.e., the latest changes to the resource calendar
(planned admin time or actual admin time posted after the resource had been
originally assigned to the task) are not being picked up automatically - In
order to bring in the latest changes, we have had to remove the resource from
the task and re-assign the resource. We are using Project 2007 Server and
Pro, Moss2007. Removing resources from a task and reassigning them seems an
unacceptable resoution to this problem. Any ideas on a better resolution?
Dots
Task level) indicates that there is a mismatch between the task calendar and
the resource calendar; i.e., the latest changes to the resource calendar
(planned admin time or actual admin time posted after the resource had been
originally assigned to the task) are not being picked up automatically - In
order to bring in the latest changes, we have had to remove the resource from
the task and re-assign the resource. We are using Project 2007 Server and
Pro, Moss2007. Removing resources from a task and reassigning them seems an
unacceptable resoution to this problem. Any ideas on a better resolution?
Dots