We created some resources with a working calendar of Mon - Thu, 10 hours a
day, where the other resources have a standard work week of Mon - Fri, 8
hours a day. When we assign a nonstandard resource and a standard resource to
the same task (a fixed duration, not effort driven task) it adjusts the
duration to accomodate the nonstandard resources schedule. For example, a 1
week task has the same dates (Mon - Fri) but it is the duration says it's 1.2
weeks (assuming that a week is Mon - Thur). When we assign just the
nonstandard resource to a task, it adjusts the dates to four days, and
duration remains the same at 1 week. Is this supposed to happen?
Rachel
day, where the other resources have a standard work week of Mon - Fri, 8
hours a day. When we assign a nonstandard resource and a standard resource to
the same task (a fixed duration, not effort driven task) it adjusts the
duration to accomodate the nonstandard resources schedule. For example, a 1
week task has the same dates (Mon - Fri) but it is the duration says it's 1.2
weeks (assuming that a week is Mon - Thur). When we assign just the
nonstandard resource to a task, it adjusts the dates to four days, and
duration remains the same at 1 week. Is this supposed to happen?