P
Phyl
Hi all,
Hope you can help figure out why this is happening.
1. Project calendar is set to UK. March 25 and March 29, 2005 are
blocked out as holidays on the UK calendar.
2. Resource calendar for "Joe Resource" is set to US, with Mar 25 & 29
as working days.
3. A task that starts on March 25 for "Joe Resource" and is set for a
fixed duration of 1 day, shows a span of 3 days. The task starts on
Friday, Mar 25, and ends on Tue, Mar 29.
Why is the resource calendar not overriding the project calendar?
Since "Joe Resource's" calendar is US, he should have only one day of
work, not 3.
The only way we can get this to work correctly is to set the Task
calendar on the individual task to US, and that seems to fix it.
However, that's not how the system should work, correct?
Any help you can provide is greatly appreciated!
Phyllis
Hope you can help figure out why this is happening.
1. Project calendar is set to UK. March 25 and March 29, 2005 are
blocked out as holidays on the UK calendar.
2. Resource calendar for "Joe Resource" is set to US, with Mar 25 & 29
as working days.
3. A task that starts on March 25 for "Joe Resource" and is set for a
fixed duration of 1 day, shows a span of 3 days. The task starts on
Friday, Mar 25, and ends on Tue, Mar 29.
Why is the resource calendar not overriding the project calendar?
Since "Joe Resource's" calendar is US, he should have only one day of
work, not 3.
The only way we can get this to work correctly is to set the Task
calendar on the individual task to US, and that seems to fix it.
However, that's not how the system should work, correct?
Any help you can provide is greatly appreciated!
Phyllis