R
Roy
I have projects that most resources use a standard calendar, but my
installation resources (generic) use a 5 day 10 hour calendar. I am using
fixed duration, non-effort driven for my tasks. Initially I assigned the
resources and their hours to my tasks with standard calendar. One 20 day
task, for example, has 7500 hours applied and MS Project told me I had 46.9
resources assigned (20 days, 8 hours = 160. 7500 divided by 160 yields the
46.9). I created a Global 5 day 10 hour calendar (not the Standard) and then
applied it to the Installation resources. I expected to see the allocation
become 37.5 resources, but the allocation did not change. I noticed when I
created the new calendar there was not an "options" choice to re-set the
start and end times to match the new calendar. Can someone help me?
installation resources (generic) use a 5 day 10 hour calendar. I am using
fixed duration, non-effort driven for my tasks. Initially I assigned the
resources and their hours to my tasks with standard calendar. One 20 day
task, for example, has 7500 hours applied and MS Project told me I had 46.9
resources assigned (20 days, 8 hours = 160. 7500 divided by 160 yields the
46.9). I created a Global 5 day 10 hour calendar (not the Standard) and then
applied it to the Installation resources. I expected to see the allocation
become 37.5 resources, but the allocation did not change. I noticed when I
created the new calendar there was not an "options" choice to re-set the
start and end times to match the new calendar. Can someone help me?