Resource calendars - MAXIMO/Project Interface

C

Christie

We use a MAXIMOProject.ini file to transfer data from MAXIMO to MS Project.
We assign crew codes, shared tools, and facilities to each job in MAXIMO.

Everytime I run the interface, it creates a new MS Project - I cannot use a
template and bring the information from MAXIMO into the template. Is there a
way to maintain a "template" calendar for the crew codes, shared tools (like
forklifts, crane weights, manlifts) and for a facility and then some how
bring that calendar into my new MS Project once the interface is ran?

Also -Does anyone know if MAXIMO calendars will transfer over into MS Project?
 