A
amkelly
I have tasks that have resources assigned to them. The
resources ahve calendars assigned to them. The resource
calendar work saturdays and sundays, the project calendar
does not. When I enter durations for the tasks, say 7
days, the elapsed time shown is actually 9 days, because
it uses the project calendar. Shouldn't it use the
Resource calendar. How can force the duration enterd to be
consistent with the resource calendar. Note: I also tried
assigning the 7-day a week resource calendar to the task,
but no change?
resources ahve calendars assigned to them. The resource
calendar work saturdays and sundays, the project calendar
does not. When I enter durations for the tasks, say 7
days, the elapsed time shown is actually 9 days, because
it uses the project calendar. Shouldn't it use the
Resource calendar. How can force the duration enterd to be
consistent with the resource calendar. Note: I also tried
assigning the 7-day a week resource calendar to the task,
but no change?