Resource Capacity Settings in additional servers ettings

S

Steve Scott

Hi, can someone remind what this option is for ie it has to be a scheduled
job overnight? How does this differ from the fact I can change a resource's
capacity by eg updating his/her calendar?
 
B

Ben Howard

Hi Steve, Is this Project Server 2007?

When you change a resource's calendar etc, it will be reflected in the
reporting DB. I'm not sure which scheduled job implements this...
 
S

Steve Scott

Hi yes PS2007. There is a schedule setting in Additional server settings
where you specify a date range. I just wanted to know what function it
performs.
 