Resource Capacity

E

Evgeni Katsarski

Hi All,
in the Resource Center some resource capacity is reported as 0h per day. I
can't find why the resource capacity is reported fine for some resources and
wrong for others. Please help. I'm using ms project 2007.



Thanks and best regards,
Evgeni
 
B

Ben Howard

Hi Evgeni,

This could be due to a calendar execption for the resource, or an effective
date coming into play. Check the resource calendar and the effective dates.
 
N

Nikki

Hi Evgeni,

This could be due to a calendar execption for the resource, or an effective
date coming into play.  Check the resource calendar and the effective dates.
--
Thanks,  Ben.

Please rate this post if it helped.http://appleparkltd.spaces.live.com/






- Show quoted text -

Hi Evgeni,

do you have calendars set up for resources? if so do these calendars
include working hrs?

also one other thing to ensure to check which shows a resource with
zero capacity in the resource centre... the user who has zero hours
reported against them ensure that where the user is set up - server
settings - manage users - user name - the option (team assignment
pool) needs to be unchecked unless you know how to use this function

hope that helps
Nikki
 
E

Evgeni Katsarski

Hi Nikki,
your assumption is correct. I found the same - resources marked with "team
assignment pool" on were reported with 0 hours capacity. When I cleared out
it capacity was reported fine.

Thanks a lot for your help,
Evgeni
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top