M
Mitch C
I am having a frustrating time trying to get a resources hours to appear in
the correct month. My company would like to track vacation hours in a MS
Project Schedule, and track the hours as part of the overall resource time
allotment.
I have loaded all names into a Schedule, and allocated the resources 100%
for the duration of their vacations. I am starting in June, and if I only
have June entered, then the hours appear correctly in the resource center
Availability view. However, if I add previous months (Jan - May, with no
hours of vacation) the resource hours for June vacation appear in the January
resource hours. I have set Start No Earlier Constraints and even Actual
Start dates set to June 1.
I thought I had it when I set the Actual Start date (the hours appeared
under June), then I added the month of April (no hours) and everything
reverted back to January.
Is this a bug? Am I doing something obviously wrong (besides tracking
vacaction in this manner - which wasn't my first choice). Thanks for any
help.
the correct month. My company would like to track vacation hours in a MS
Project Schedule, and track the hours as part of the overall resource time
allotment.
I have loaded all names into a Schedule, and allocated the resources 100%
for the duration of their vacations. I am starting in June, and if I only
have June entered, then the hours appear correctly in the resource center
Availability view. However, if I add previous months (Jan - May, with no
hours of vacation) the resource hours for June vacation appear in the January
resource hours. I have set Start No Earlier Constraints and even Actual
Start dates set to June 1.
I thought I had it when I set the Actual Start date (the hours appeared
under June), then I added the month of April (no hours) and everything
reverted back to January.
Is this a bug? Am I doing something obviously wrong (besides tracking
vacaction in this manner - which wasn't my first choice). Thanks for any
help.