Hi all,
In Project 2003 WebAccess by using the View Availability option in the
Resource Center I can access an useful Resource Availability view for
pre-selected resources.
I however noticed that:
Default view options are Assignment Work by Resource, Assignment Work by
Project, Remaining Availability and Work; I’ve found no way to define an
additional view option for this page, not even by the Manage views
administrative functionality (it seems that only Projects, Project Center,
Resource Center, Resource Assignment, Portfolio Analyzer and Timesheet pages
could be customized here); is there a way to add a customized view option in
the Resource Availability view?
The longest period unit for the analysis is the week; is there a way to have
a monthly distribution? or (in second istance) is there a way to have weeks
starting on Monday and not on Sunday?
Thank you,
Angelo
In Project 2003 WebAccess by using the View Availability option in the
Resource Center I can access an useful Resource Availability view for
pre-selected resources.
I however noticed that:
Default view options are Assignment Work by Resource, Assignment Work by
Project, Remaining Availability and Work; I’ve found no way to define an
additional view option for this page, not even by the Manage views
administrative functionality (it seems that only Projects, Project Center,
Resource Center, Resource Assignment, Portfolio Analyzer and Timesheet pages
could be customized here); is there a way to add a customized view option in
the Resource Availability view?
The longest period unit for the analysis is the week; is there a way to have
a monthly distribution? or (in second istance) is there a way to have weeks
starting on Monday and not on Sunday?
Thank you,
Angelo