Resource column

X

Xandra

Hi! I tried to create several resource columns, since I have several
different resources. But all the columns showed the same resource, no matter
the changes I did in each one.

How can I create this resource columns, so they can show different
information?
 
J

JulieD

Hi Xandra

when assigning multiple resources to a task (which, by the way, is
discouraged - generally tasks should be broken down to the level where, as
far as possible, only 1 resource works on the tasks - but that's a topic for
a different discussion) ... you enter them all in the same resource column,
not separate columns for each resource. Alternatively, you can double click
on the task and go to the resource tab and enter them each on a different
line - which might be easier.

however, having said that, i find the best way (for a number of reasons -
check out www.tinyurl.com/2xbhc for more details) to assign resources is to
use the Task Entry view (view / more views / task entry).

hope this helps
Cheers
JulieD
 