J
John Sitka
What is the graphical representation to show this when the logical plan is inaccurate.
ex. 4 hour task was scheduled Thursday but it was almost completed
previous Monday.
The case is the plan assumed finish to start linkages surrounding this task
but a resourceful resource realized he could get 3 hours completed well before the
predecessor finished. If a planner dosen't know this before had how does one
display the actual work done at the actual time it was done! A circular arguement
could ensue here but for this case assume that the planner does not know
"every" nuance of "every" profession and therefore might make a finish to start link
when some other type might be more suitable. I guess what I'm looking for
is an actual timeline bound display of when work was performed as well as a progess
bar over the incorrectly split (but effectively unknowable) task bar.
Thanks.
Here is a 1st position example. A project was scheduled to start with task A on Thursday
but the resource recorded actuals on the previous Monday. He got an early start.
ex. 4 hour task was scheduled Thursday but it was almost completed
previous Monday.
The case is the plan assumed finish to start linkages surrounding this task
but a resourceful resource realized he could get 3 hours completed well before the
predecessor finished. If a planner dosen't know this before had how does one
display the actual work done at the actual time it was done! A circular arguement
could ensue here but for this case assume that the planner does not know
"every" nuance of "every" profession and therefore might make a finish to start link
when some other type might be more suitable. I guess what I'm looking for
is an actual timeline bound display of when work was performed as well as a progess
bar over the incorrectly split (but effectively unknowable) task bar.
Thanks.
Here is a 1st position example. A project was scheduled to start with task A on Thursday
but the resource recorded actuals on the previous Monday. He got an early start.