Resource Cost Calculation Incorrect

S

SJY`1

Hi,

I have an enterprise resource who is assigned to a number of tasks in an
enterprise project, this enterprise resource has a single cost assigned to
him in the cost rate tables.

In the project, the resource is assigned to 3 tasks, all of the same
duration, all 100% loaded, but MS Project is calculating a different cost for
that resource for each task.

Any help would be appreciated... Thanks!
 
R

Rod Gill

Cost isn't necessarily directly dependant on Duration. What is the Work for
each assignment? Are any other Resources assigned and are there any fixed
costs?

--

Rod Gill
Microsoft MVP for Project

Author of the only book on Project VBA, see:
http://www.projectvbabook.com
 