Resource cost clarification

J

Jamie Hart

How do I set specific parameters to my material resouce cost? In other
words, 10ft. of pipe costs $15 and for task 3 I will use 3 units (30 ft.).
 
J

JulieD

Hi Jamie

the way i approach it is in the Resource Sheet enter Pipe as the resource
name, choose Material as the Type and in the Material Label column type 10ft
and in the Standard Rate column type $15
now when you use the pipe type 3 in the units field against the "pipe"
resource. (i do this in the resource tab of the task information dialog
box).

Regards
JulieD
 
S

Steve House

In addition to Julie's suggestion, for resources whose total consumption is
related to the task duration, like fuel that is burned at 10 litres/hr for
the duration of the task, instead of entering total units to be used in the
resource assignment dialog box, enter the rate of usage. In my example, the
resource name would be gasoline, the type would be material, the units would
be litres, and the standard rate would be the cost/litre. When entered into
the resource assignment dialog you would put "10/hr" in the units column.
Then the total used will change as the task gets longer or shorter. Just
entering the number without the "/hr" means that number of units will be
used over the duration of the task regardless of its duration, exactly what
should happen with your pipe (to get from Here to There will require 30 feet
of pipe, 3 units, regardless of whether it takes you 4 hours or 6 hours to
install it).
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top