I added Cost1 to the resource sheet in PS07 within the Ent Global
I now wanted to type in a cost amount for an internal cost. Say i want to
type in $100
However, when i check out the Resource into Project 2007, i cannot enter any
value into Cost1 or any of the Cost fields (Cost1-Cost10)
Am i missing something why i can't enter a cost value at the resource level
into resource fields Cost1-10?
I can enter data into the cost/hr fields such as Std Rate, Ovt and
Cost/Use...
I can enter other Resource Enterprise field data...
any insight would be appreciated
I now wanted to type in a cost amount for an internal cost. Say i want to
type in $100
However, when i check out the Resource into Project 2007, i cannot enter any
value into Cost1 or any of the Cost fields (Cost1-Cost10)
Am i missing something why i can't enter a cost value at the resource level
into resource fields Cost1-10?
I can enter data into the cost/hr fields such as Std Rate, Ovt and
Cost/Use...
I can enter other Resource Enterprise field data...
any insight would be appreciated