P
Paul Billings
Hi all,
I'm looking for some opinions regarding a real-world issue: resource
downtime. Let's say you've gotten your schedule nicely planned and
leveled appropriately. Rather unfortunately, some resources will
likely not have anything to do at times. One example is a slack task:
task T1 is scheduled for M-Th (4 days), T2 is scheduled for M-Tu (2
days), and both are predecessors of T3 (necessarily starting Friday).
T2 is the slack task.
What I see typically is that the resource will take longer than 2 days
to complete T2 (driving up cost), simply because they have nothing
else to do. Seems like the only choices are 1) put the resource on
another project (or company-sponsored "indirect") for W-Th, 2) start
some other task in this project early (which potentially drives up
that cost for the same reason), or 3) suggest that the resource have a
nice "break" -- at the expense of their vacation time :-(.
Additionally, this avoidance of downtime discourages the resource from
completing a task early -- meaning that costs will only ever increase.
Are there any other options I've missed? Is this just the sad truth
of multiple-resource projects?
Paul
I'm looking for some opinions regarding a real-world issue: resource
downtime. Let's say you've gotten your schedule nicely planned and
leveled appropriately. Rather unfortunately, some resources will
likely not have anything to do at times. One example is a slack task:
task T1 is scheduled for M-Th (4 days), T2 is scheduled for M-Tu (2
days), and both are predecessors of T3 (necessarily starting Friday).
T2 is the slack task.
What I see typically is that the resource will take longer than 2 days
to complete T2 (driving up cost), simply because they have nothing
else to do. Seems like the only choices are 1) put the resource on
another project (or company-sponsored "indirect") for W-Th, 2) start
some other task in this project early (which potentially drives up
that cost for the same reason), or 3) suggest that the resource have a
nice "break" -- at the expense of their vacation time :-(.
Additionally, this avoidance of downtime discourages the resource from
completing a task early -- meaning that costs will only ever increase.
Are there any other options I've missed? Is this just the sad truth
of multiple-resource projects?
Paul