Resource graph customization

A

Aaron

I would like to be able to visualize the tasks represented by each allocation
bar in the resource graph view, while still in that view. I currently have
to toggle back and forth between the resource graph view and full gantt,
which is cumbersome. Any help would be great.
 
M

Mike Glen

Choose either of the suggestions made in your previous post.

Mike Glen
Project MVP
 