Resource Graph for more than one source?

J

John

Patience said:
Is it possible to view a combined resource graph for two or more resources?

Patience,
Yes. Use a split view with a resource type view (e.g. Resource Sheet,
Resource Usage, etc.) in the top pane and the Resource Graph in the
bottom pane. Activate the bottom pane and go to Format/Barstyles. Select
the desired graph element, color and pattern for Selected Resources
(left side of Bar Styles window) and "Don't Show" for "Resource" on the
right side of the window. Hit "ok". The graph will now show a combined
graph of however many resources are selected in the top pane.

Hope this helps.
John
Project MVP
 
M

Mike Glen

Hi Patience,

Welcome to the Microsoft Project newsgroup :)

Please see FAQ Item: 38. Combined Resource Graph

FAQs, companion products and other useful Project information can be seen at
this web address: http://www.mvps.org/project/

Hope this helps - please let us know how you get on:)

Mike Glen
Project MVP
 
J

John

Mike Glen said:
Hi Patience,

Welcome to the Microsoft Project newsgroup :)

Please see FAQ Item: 38. Combined Resource Graph

FAQs, companion products and other useful Project information can be seen at
this web address: http://www.mvps.org/project/

Hope this helps - please let us know how you get on:)

Mike Glen
Project MVP


Mike,
Sorry, I forgot about the FAQ on that issue.

John
 