Resource Graph labels

S

Steve268

Hi,

sorry to be asking another daft question on the forum !
Does anyone know if it is possible to display labels on the Resource Graph?
i.e. when reviewing resource A the bar graph shows his allocation, but also
what he is allocated to?
I know you can view this info through the split screen, but it would be
useful if i could view this as a label on the graph.

Many thanks (in advance)

Steve.
 
J

JulieS

Hello Steve268,

Not a daft question at all -- but sad to say, as far as I know, not
possible. The Resource Graph summarizes resource work per time phase
(usually day). So, if a resource is assigned to 3 tasks during the day,
the graphs just shows his/her total work.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 