T
Thomas
Hi all,
anyway that this discussion is not the only one on the issue
"inactive" resources...I would like to bring it to an end
(as I am also looking for the best solution).
Situation as follows...
Resource ABC has left the company.
After some weeks I set the status to inactive ...assuming that no
remaing work is left. (did not check)
Afterwards our project managers get error messages from project server
spooler. (cannot build resource account / 0x8C040017)
This will be based on the fact that ABC still has remaining work ...
But how to proceed? How to set all remaining work to ZERO ... the
easiest way?
(A) Do I have to open all projects, where ABC has work to do or is a
team member and set
remaining work to zero...republish changes...? Afterwards set the
account status to inactive.
(B) What about the following approach?
Instead of deactivating the user, changing the logon to Project Server
Authentication, set all the remaining work --> 0
Sending ALL Updates...Waiting for project managers updates...and then
deactivate the resource!?
As I wanted to avoid project spooler messages I did not deactivate
accounts, but set them to
workgroup none...and erased the windows account. But then the managers
also get other spooler
errors...
Is there no easy way how to set remaining work to zero and set
resource status to inactive?
And finally...when inactive resources don't have remaining work...we
won't get the spooler error?
Help
Thomas
PS: We're using Project / Server 2003
anyway that this discussion is not the only one on the issue
"inactive" resources...I would like to bring it to an end
(as I am also looking for the best solution).
Situation as follows...
Resource ABC has left the company.
After some weeks I set the status to inactive ...assuming that no
remaing work is left. (did not check)
Afterwards our project managers get error messages from project server
spooler. (cannot build resource account / 0x8C040017)
This will be based on the fact that ABC still has remaining work ...
But how to proceed? How to set all remaining work to ZERO ... the
easiest way?
(A) Do I have to open all projects, where ABC has work to do or is a
team member and set
remaining work to zero...republish changes...? Afterwards set the
account status to inactive.
(B) What about the following approach?
Instead of deactivating the user, changing the logon to Project Server
Authentication, set all the remaining work --> 0
Sending ALL Updates...Waiting for project managers updates...and then
deactivate the resource!?
As I wanted to avoid project spooler messages I did not deactivate
accounts, but set them to
workgroup none...and erased the windows account. But then the managers
also get other spooler
errors...
Is there no easy way how to set remaining work to zero and set
resource status to inactive?
And finally...when inactive resources don't have remaining work...we
won't get the spooler error?
Help
Thomas
PS: We're using Project / Server 2003