R
Reuter
PS2003ent.
How do I change a resources yearly calendar to reflect their vacation time
weather it be 1week, 2weeks or 3weeks. I need their calendar to reflect that
they are here 100% of the time for the 85% they are in the office. Right now
I have to change their availability for the year to 85% so they are not
booked while on vacation.
How do I change a resources yearly calendar to reflect their vacation time
weather it be 1week, 2weeks or 3weeks. I need their calendar to reflect that
they are here 100% of the time for the 85% they are in the office. Right now
I have to change their availability for the year to 85% so they are not
booked while on vacation.