I am using MSOP 2007 desktop. I have created a resource pool. Some of my
resources work less than 40 hours per week. I have set their resource
calendar to reflect this.
My question is:
Can I pull how many hours a resource can be used per month? I just want to
know from the calendar perspective, total # of work hours per month. I do
not want to account for any assignments. I need to export this information
for each resource in the pool to excel to do reporting.
resources work less than 40 hours per week. I have set their resource
calendar to reflect this.
My question is:
Can I pull how many hours a resource can be used per month? I just want to
know from the calendar perspective, total # of work hours per month. I do
not want to account for any assignments. I need to export this information
for each resource in the pool to excel to do reporting.