seth
I have the schedule as below in Project 2007:
Task1 - Res1 (100%) - 21 days (duration)
Task2 - Res2 (100%) - 45 days (duration)
Both have same start dates. After task 1 is complete, Res1 will join task2
as 100%.
How do I make this type of allocation? If I add Res1 to Task2 and allocate
100% and level, the duration for task2 is not reducing considerably as
expected. It is changing to 43.5 days only.
Thanks for your help.
seth
Task1 - Res1 (100%) - 21 days (duration)
Task2 - Res2 (100%) - 45 days (duration)
Both have same start dates. After task 1 is complete, Res1 will join task2
as 100%.
How do I make this type of allocation? If I add Res1 to Task2 and allocate
100% and level, the duration for task2 is not reducing considerably as
expected. It is changing to 43.5 days only.
Thanks for your help.
seth