Simmons_RJ
I have two tasks (Task 1 and Task 2) on a project plan that I would like to
keep to gether that are assigned different resources (Res 1 and Res 2). When
leveling the plan Res 1 has availability much earlier than Res 2 and
therefore a significant time gap is created in the two tasks. Is there
anyway (other than manually) of keeping the tasks together when the leveling
is done?
Thanks,
RS