Resource Leveling Macro

P

pec

The challenge is to have resources loaded according to allocation. For
example, a resource is assigned to a particular Cost Account at 50% with many
tasks, how can I add the resource to these tasks to equate to a total of 50%?
Is there a macro than can be created to automatically level the resource or
spread the resource equally across assignments as allocated and over the
total time period?
 
J

Jan De Messemaeker

Hi,

There is no spreading macro, at least not one I know of.
The way to handle this is
in the project set the working time to 4 h/d
assign teh resoruce 100% to all
Now use Project's leveling

HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 
P

pec

Jan,

What if the resource is assigned to several different cost accounts on the
project? Would I be able to specify work hours for each cost account? calendar
 
P

pec

Sorry, cost account is in reference to earned value. So, in this case it
would be work breakdown or summary task
 
J

Jan De Messemaeker

Hi,

If respecting this % of time is so important (which is shocking to me, I
would always allocate resources to the most urgent tasks, not in less
relevant percentages) , I see only a very complicated option, that doesn't
even work in all cases:

* Develop the necessary calendars representing the desired % of time.

Leave the resources at 100%, full day calendars
To the TASKS of a summary task, assign a task calendar representing the %
the resources will be allowed to work on this summary task

Level with a day by day setting

Note: this doesn't work if different resources have different allocation %
within the same summary task
HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 
P

pec

Jan,

It is important based on the fact that this data is also extracted for
earned value. Therefore, the resource loading must equates to the baseline
as close as possible.

Thanks for feedback
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top