P
pec
The challenge is to have resources loaded according to allocation. For
example, a resource is assigned to a particular Cost Account at 50% with many
tasks, how can I add the resource to these tasks to equate to a total of 50%?
Is there a macro than can be created to automatically level the resource or
spread the resource equally across assignments as allocated and over the
total time period?
example, a resource is assigned to a particular Cost Account at 50% with many
tasks, how can I add the resource to these tasks to equate to a total of 50%?
Is there a macro than can be created to automatically level the resource or
spread the resource equally across assignments as allocated and over the
total time period?