grimgroups
I'm using Project Pro 2003 SP1. I can not seem to get the leveling
working at all for a Published Enterprise Project. Leveling works fine
when the resources are tagged as local users (non-enterprise). I
created a simple 4 task project using two Enterprise Resources and I
can not level the project. The tasks remain stacked ontop of each
other. The task durations are between 1 and 2 days. The leveling
settings are Auto, Hour by Hour, entire project, priority/standard, and
no checkboxes checked. I tried different combinations and nothing
seems to work. Are there settings on my Project Server that I should
look at?
Thanks.
Grim
working at all for a Published Enterprise Project. Leveling works fine
when the resources are tagged as local users (non-enterprise). I
created a simple 4 task project using two Enterprise Resources and I
can not level the project. The tasks remain stacked ontop of each
other. The task durations are between 1 and 2 days. The leveling
settings are Auto, Hour by Hour, entire project, priority/standard, and
no checkboxes checked. I tried different combinations and nothing
seems to work. Are there settings on my Project Server that I should
look at?
Thanks.
Grim