Resource leveling problem

M

marleixo

Friends,
In first place, sorry about my english, i'm brazilian... so my english
was not so good.. :/

I have a problem with the MSProject and Project Server resource
levelling

When I have the same resource in more than 1 project the resource
still overallocated in the resource usage and resource sheet and when
I make resource levelling the task is "pushed" because of the
overallocation...

I need that the allocation of my resources works one by one on my
projects, if the resource is allocated in another project I dont have
to care about this... Our resources are not "people", they are
generic...

I can use local resources, but we already have a default for the names
of the resources and another datas of the resources, so I cannot use
local resources....

My question is... there are some way to project dont care aboult the
allocation of another projects??
If I simply delete on the resource usage the register of the another
projects it works... but when I close and open the project again the
assingment with another project name cames back...

Thanks everyone anyway...
 
M

marleixo

Friends,
In first place, sorry about my english, i'm brazilian... so my english
was not so good.. :/

I have a problem with the MSProject and Project Server resource
levelling

When I have the same resource in more than 1 project the resource
still overallocated in the resource usage and resource sheet and when
I make resource levelling the task is "pushed" because of the
overallocation...

I need that the allocation of my resources works one by one on my
projects, if the resource is allocated in another project I dont have
to care about this... Our resources are not "people", they are
generic...

I can use local resources, but we already have a default for the names
of the resources and another datas of the resources, so I cannot use
local resources....

My question is... there are some way to project dont care aboult the
allocation of another projects??
If I simply delete on the resource usage the register of the another
projects it works... but when I close and open the project again the
assingment with another project name cames back...

Thanks everyone anyway...

--
Marcio Aleixo
Project Management Consultant / EPM - Microsoft Project Server
E-mail: (e-mail address removed) / (e-mail address removed)
Tel: +55(21)8182-8661 / (21)2515-7627

Sorry... I'm using project server 2003 SP2a and project professional
SP2
Thanks
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top