A
Akram
Hi,
I am using leveling in microsoft project professional with no problem,
however when i use it when connect to the project server, i face the
following problem with leveling:
I have a resource assigned to 2 tasks at the same time and schedule, when i
do leveling it assigns the resource the first task accordingly, however it
assigns the second resource 2 weeks from its date, although the first task is
only 2 days. i tried seeing the availability and found it was not utilized
for a whole week. The leveling delay field shows 10 days leveling delay !!
i used the following settings with leveling:
1. ID Only
2. all values are unchecked
3. Manual
4. Hour by Hour
i tried using it with different settings but with no success, can someone
please help me out.
I am using leveling in microsoft project professional with no problem,
however when i use it when connect to the project server, i face the
following problem with leveling:
I have a resource assigned to 2 tasks at the same time and schedule, when i
do leveling it assigns the resource the first task accordingly, however it
assigns the second resource 2 weeks from its date, although the first task is
only 2 days. i tried seeing the availability and found it was not utilized
for a whole week. The leveling delay field shows 10 days leveling delay !!
i used the following settings with leveling:
1. ID Only
2. all values are unchecked
3. Manual
4. Hour by Hour
i tried using it with different settings but with no success, can someone
please help me out.