A
Akram
Hi,
I am using resource leveling in project server and it seems there is a
problem in the way it is leveling resources. i have been using it on project
professional with no problem however when i am using it with the EPM it
creates the following problem:
my settings are:
Manual Leveling is Enabled
Level Proposed Resources is the only checked value
Default Task Type is: Fixed Work
The leveling assigns tasks with huge difference in timing meaning it leaves
1 week free for a resource with no reason, although this resource is not
allocated except to this project and even i tried doing it with several other
resources still the same.
second it overallocates resources giving them like 16 hours in a day and
sometimes allocates them for only 4 hours a day !!
Finally, i discovered when i open my project plan in project professional
without being connected to project server everything works fine, however when
i open the plan while i am connected to project server the allocation starts
doing those crazy stuff. I think this could be a problem with Global
Enterprise Template, as the project without being published just by opening
it while being connected to project server faces those above problems.
I am experiencing this problem for the past 2 months and not a single person
were able to solve it.
I am using resource leveling in project server and it seems there is a
problem in the way it is leveling resources. i have been using it on project
professional with no problem however when i am using it with the EPM it
creates the following problem:
my settings are:
Manual Leveling is Enabled
Level Proposed Resources is the only checked value
Default Task Type is: Fixed Work
The leveling assigns tasks with huge difference in timing meaning it leaves
1 week free for a resource with no reason, although this resource is not
allocated except to this project and even i tried doing it with several other
resources still the same.
second it overallocates resources giving them like 16 hours in a day and
sometimes allocates them for only 4 hours a day !!
Finally, i discovered when i open my project plan in project professional
without being connected to project server everything works fine, however when
i open the plan while i am connected to project server the allocation starts
doing those crazy stuff. I think this could be a problem with Global
Enterprise Template, as the project without being published just by opening
it while being connected to project server faces those above problems.
I am experiencing this problem for the past 2 months and not a single person
were able to solve it.