I am using resource leveling in project server and it seems there is a
problem in the way it is leveling resources. i have been using it on project
professional with no problem however when i am using it with the EPM it
creates the following problem:

my settings are:
Manual Leveling is Enabled
Level Proposed Resources is the only checked value
Default Task Type is: Fixed Work

The leveling assigns tasks with huge difference in timing meaning it leaves
1 week free for a resource with no reason, although this resource is not
allocated except to this project and even i tried doing it with several other
resources still the same.

second it overallocates resources giving them like 16 hours in a day and
sometimes allocates them for only 4 hours a day !!

Finally, i discovered when i open my project plan in project professional
without being connected to project server everything works fine, however when
i open the plan while i am connected to project server the allocation starts
doing those crazy stuff. I think this could be a problem with Global
Enterprise Template, as the project without being published just by opening
it while being connected to project server faces those above problems.


I am experiencing this problem for the past 2 months and not a single person
were able to solve it.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top