S
Shawn Everingham
Project A is a short, operational type of plan. These plans run for a quarter
and contain operational type activities, like meetings, quarterly goals, etc.
Project B is utilizing Resource Z, whom is also an enterprise resource on
Project A.
In Project B, the Resource Usage View shows Resource Z to still have work
planned for Project A. Resource Usage View shows allocated time for Resource
Z into the future, yet Project A shows all tasks to have Zero Remaining Work
and ALL tasks 100% complete. Project A has been saved and published several
times. Project A resource usage sheet shows no work for Project A for
Resource Z. I have even gone to the Resource Center in PWA and selected
Resource Z then View Availability. Even Project Server shows that this
project still has work assigned to Resource Z and has allocated work into the
future for Project A.
What gives? how can I effectively level a resource, if all plans including
the server, show enterprise resource Z to have work...although the source
plan is 100% complete????
Help???? Thanks!
and contain operational type activities, like meetings, quarterly goals, etc.
Project B is utilizing Resource Z, whom is also an enterprise resource on
Project A.
In Project B, the Resource Usage View shows Resource Z to still have work
planned for Project A. Resource Usage View shows allocated time for Resource
Z into the future, yet Project A shows all tasks to have Zero Remaining Work
and ALL tasks 100% complete. Project A has been saved and published several
times. Project A resource usage sheet shows no work for Project A for
Resource Z. I have even gone to the Resource Center in PWA and selected
Resource Z then View Availability. Even Project Server shows that this
project still has work assigned to Resource Z and has allocated work into the
future for Project A.
What gives? how can I effectively level a resource, if all plans including
the server, show enterprise resource Z to have work...although the source
plan is 100% complete????
Help???? Thanks!