J
JW
Hi,
I'm working on a schedule which includes 12 resource, each
with about 6 months worth of tasks. When I do leveling,
Projects pushes a few days worth of task assigned for a
particular resource all the way to right around
12/31/2049. The end result is that the resoure has some
tasks schedule up front, then 40 years worth of 0-hour
working weeks, then with a days worth of the remainder of
a task in December of 2049. This behavior happens randomly
from each leveling. But two particular resources among all
seem to attract this treatment.
Can anyone give me a clue as to what MSProject is trying
to do here?
Thanks in advance.
I'm working on a schedule which includes 12 resource, each
with about 6 months worth of tasks. When I do leveling,
Projects pushes a few days worth of task assigned for a
particular resource all the way to right around
12/31/2049. The end result is that the resoure has some
tasks schedule up front, then 40 years worth of 0-hour
working weeks, then with a days worth of the remainder of
a task in December of 2049. This behavior happens randomly
from each leveling. But two particular resources among all
seem to attract this treatment.
Can anyone give me a clue as to what MSProject is trying
to do here?
Thanks in advance.