M
matt
Thanks for all the help earlier on effort vs duration. Now I have a question
on levelling. I have read the Levelling FAQs that I saw referenced in other
posts, but I am curious about this behavior of Project.
After attempting to Level Resources, Project complains that it cannot level
for a set of dates, June 27-July 3. When I looked at what Project had
scheduled for that day, we had one sub-task of a project and a completely
unrelated task, scheduled for the same dates. There was no relationship
between the tasks, other than that both must be completed to meet our
"Complete & Tested" Milestone.
Oddly enough, I also noted that from May 22-Jun 9, Project scheduled NO work
at all for my resource.
So I was wondering, why didnt project move the unrelated task (that has no
predecessors or constraints) for May 22- Jun 9? I manually fixed this by
making the task start on May 22. This also resolved all of my resource
leveling issues.
Any thoughts on this strange behavior?
on levelling. I have read the Levelling FAQs that I saw referenced in other
posts, but I am curious about this behavior of Project.
After attempting to Level Resources, Project complains that it cannot level
for a set of dates, June 27-July 3. When I looked at what Project had
scheduled for that day, we had one sub-task of a project and a completely
unrelated task, scheduled for the same dates. There was no relationship
between the tasks, other than that both must be completed to meet our
"Complete & Tested" Milestone.
Oddly enough, I also noted that from May 22-Jun 9, Project scheduled NO work
at all for my resource.
So I was wondering, why didnt project move the unrelated task (that has no
predecessors or constraints) for May 22- Jun 9? I manually fixed this by
making the task start on May 22. This also resolved all of my resource
leveling issues.
Any thoughts on this strange behavior?