L
Leslie Peterson
I'm having difficulty using resource leveling. There are plenty of tasks
assigned to the resources in question that are 1-2 hours in duration.
Resource leveling is not assigning 8 hours worth of project time on any day.
It varies between 3.77 and 7 hours. In the global resource pool, the
resources are showing as available 100% for all dates.
Resources are being assigned to multiple project files and in a simple
administrative project.
I don't expect this to be solved via a newsgroup post. I'm really hoping for
suggestions on things to check. Any recommendations would be greatly
appreciated.
assigned to the resources in question that are 1-2 hours in duration.
Resource leveling is not assigning 8 hours worth of project time on any day.
It varies between 3.77 and 7 hours. In the global resource pool, the
resources are showing as available 100% for all dates.
Resources are being assigned to multiple project files and in a simple
administrative project.
I don't expect this to be solved via a newsgroup post. I'm really hoping for
suggestions on things to check. Any recommendations would be greatly
appreciated.