Resource Leveling

P

Perl

Hi,

I have Project Server 2003.
I have a question about resources:

For example, I have 3 projects with 1 resource.
I want to assign him to Gantt 1 20%, Gantt 2 20%, and Gantt 3 60%.
At Gantt 1 he has 3 tasks without link between them. the same at the other
gantts, all of them are at the same time.
Now I want to level the resource. How do I make sure that tasks will
schedule for Gantt 1 at max. 20% units and
not parallelly ?

Thanks

P.
 
G

Gérard Ducouret

Hello Perl,

In each plan, assign your resource to each elementary task as you want :
20%, 60% (the easiest way is to use the Assign Resource dialog for that)
Then make sure your 3 plans are open, and run the leveling feature:
Tools / Level resources / Level Now

NB : set Leveling order : Priority; Standard, if you want to set different
priorities to your tasks or projects

Gérard Ducouret
 
P

Perl

Hello Grard,

Thanks you, but......

How do I make sure the leveling will not schedule all 3 tasks with 20%
together.
I don't want to set a differnet priority for each task.

Any other idea ?

Thanks

P.
 
G

Gérard Ducouret

Perl,
That's the first aim of leveling feature to do that.
You can check the result in the Leveling Gantt and in the Resource Usage
view of Project.
Gérard Ducouret
 