I
ITPM
I've read a lot of great posts regarding resource leveling across multiple
projects.
We upgraded to MS Project Server 2007 a few months ago. We have about 150
resources, and about 85 projects in our 'portfolio'. Resources work on
projects and "support plans" and log their time via Task Sheets each week.
Close to every resource we have is overallocated...it's disturbing.
I know that leveling is pretty intensive. We have to open up each project
that a particular resource is assigned to and level across the gamut. I also
know that leveling does nothing more than delay projects/tasks until the
resource IS available. This would honk off a LOT of PMs whose schedules
change as a result.
Is there any way to recover and do this properly? We're certainly not
planning our time well, nor allcoating resources properly. We are just about
to unleash MS Project Portfolio Server, but I hesistate due to this issue.
Thanks!
projects.
We upgraded to MS Project Server 2007 a few months ago. We have about 150
resources, and about 85 projects in our 'portfolio'. Resources work on
projects and "support plans" and log their time via Task Sheets each week.
Close to every resource we have is overallocated...it's disturbing.
I know that leveling is pretty intensive. We have to open up each project
that a particular resource is assigned to and level across the gamut. I also
know that leveling does nothing more than delay projects/tasks until the
resource IS available. This would honk off a LOT of PMs whose schedules
change as a result.
Is there any way to recover and do this properly? We're certainly not
planning our time well, nor allcoating resources properly. We are just about
to unleash MS Project Portfolio Server, but I hesistate due to this issue.
Thanks!