R
Riko Wichmann
Hi all,
I don't think, I understand resource leveling in MS Project.
Here is the situation:
The task is to optimize the preparation of a certain component for
further assembly. Let's say, I have 10 components coming in with a rate
of 1/week. Then I have the preparation steps planned with resources and
availability, and with dependencies. It's a linear series, when each
step as one and one one predecessor. These steps I copy 10 times and
link them with the arrival date of those 10 components. Nothing else is
set, no priorities, no constraints or anything. Doesn't sound to
complicated so far.
Now, the limiting factor is the availability of resources. That's where
I thought resource leveling would help.
If I look at the resource sheet, I select in the resource leveling
toolbox the overallocation level in a way, that all overallocated
resources get the yellow exclamation mark in the info column telling me
that I should level the resource using for example "hour by hour".
If I do that, using otherwise the standard settings, I get rid of some
of the overallocation but not all: 2 out of 4 remain overallocated.
Consecutive levelings don't help.
There are no constraints otherwise on any of the tasks which would stop
project from just shifting things until there is no overallocation. Why
does it not do that?
Next step would be: What happens if my components arrive with a rate of
2/week. You would assume, the whole process is AT LEAST as fast as with
1/week. However, after resource leveling it takes LONGER????
Using Project Standard 2002
Thanks for any hint,
Riko
I don't think, I understand resource leveling in MS Project.
Here is the situation:
The task is to optimize the preparation of a certain component for
further assembly. Let's say, I have 10 components coming in with a rate
of 1/week. Then I have the preparation steps planned with resources and
availability, and with dependencies. It's a linear series, when each
step as one and one one predecessor. These steps I copy 10 times and
link them with the arrival date of those 10 components. Nothing else is
set, no priorities, no constraints or anything. Doesn't sound to
complicated so far.
Now, the limiting factor is the availability of resources. That's where
I thought resource leveling would help.
If I look at the resource sheet, I select in the resource leveling
toolbox the overallocation level in a way, that all overallocated
resources get the yellow exclamation mark in the info column telling me
that I should level the resource using for example "hour by hour".
If I do that, using otherwise the standard settings, I get rid of some
of the overallocation but not all: 2 out of 4 remain overallocated.
Consecutive levelings don't help.
There are no constraints otherwise on any of the tasks which would stop
project from just shifting things until there is no overallocation. Why
does it not do that?
Next step would be: What happens if my components arrive with a rate of
2/week. You would assume, the whole process is AT LEAST as fast as with
1/week. However, after resource leveling it takes LONGER????
Using Project Standard 2002
Thanks for any hint,
Riko