Hi,
I have a master planning for a team of developers that tells them o
which project they need to work. I use priorities to have the resourc
levelling done.
Is the following possible with MS project? I have someone assigned to
task last week. For whatever reason, this person could not do this task
or only partly. I fill in the actual work so project knows how much ha
been done. I now want to redo the resource levelling, as of now, and
want MS project to move the task of last week to a point after today, a
it was not finished. So I don't want to leave it in the past (las
week).
Thanks
Cedri
I have a master planning for a team of developers that tells them o
which project they need to work. I use priorities to have the resourc
levelling done.
Is the following possible with MS project? I have someone assigned to
task last week. For whatever reason, this person could not do this task
or only partly. I fill in the actual work so project knows how much ha
been done. I now want to redo the resource levelling, as of now, and
want MS project to move the task of last week to a point after today, a
it was not finished. So I don't want to leave it in the past (las
week).
Thanks
Cedri