L
Leyton
Hi All,
This one is a first post and first MS Project problem I
haven't figured out . . . but then I recently started
using this version.
Anyway, here's my example in an attempt to resolve a much
bigger (and real) project: I've got a resource working on
3 tasks over 4 days, 8 hours each day.
- The first task takes 20 hours total effort,
- The second task starts 4 hours later with 10 hours total
effort,
- The third task is on the last day for 2 hours.
- The constraint type is 'Start No Earlier Than'
- I checked to make sure the Working Time in the Project
Calendar was actually an 8 hour day
I've tried:
- standard levelling (using the drop menus),
- adjusting the units available for the resource on each
task,
- different contours in the assignment information, and
- manual entering the numbers in the Resource Usage window.
No matter what I try, at least one view shows my Resource
(me in the above example) as extremely over allocated for
at least one day -- even though the numbers (on the last
try above) show 8 hours each day (the Resource Graph view
says I'm at 175%). I'd really like to solve this since the
real project has 22 people and over 300 tasks in the
project.
Help! :-(
Thanks,
Leyton
This one is a first post and first MS Project problem I
haven't figured out . . . but then I recently started
using this version.
Anyway, here's my example in an attempt to resolve a much
bigger (and real) project: I've got a resource working on
3 tasks over 4 days, 8 hours each day.
- The first task takes 20 hours total effort,
- The second task starts 4 hours later with 10 hours total
effort,
- The third task is on the last day for 2 hours.
- The constraint type is 'Start No Earlier Than'
- I checked to make sure the Working Time in the Project
Calendar was actually an 8 hour day
I've tried:
- standard levelling (using the drop menus),
- adjusting the units available for the resource on each
task,
- different contours in the assignment information, and
- manual entering the numbers in the Resource Usage window.
No matter what I try, at least one view shows my Resource
(me in the above example) as extremely over allocated for
at least one day -- even though the numbers (on the last
try above) show 8 hours each day (the Resource Graph view
says I'm at 175%). I'd really like to solve this since the
real project has 22 people and over 300 tasks in the
project.
Help! :-(
Thanks,
Leyton