D
Des
I asked this question yesterday in another group, but I
did not explain my problem fully.
I am trying to schedule a project having large necessary
lags between activities.When you set the required lag,you
effectively tie each activity to the chosen lag. Even if
you move one activity, you move them all,because the lag
is not seen to give any free slack to any activity.
In this project there are over 150 activities, so it
seems impossible to level the demand for resources.
My question then is to ask you if there is anyway that
the lag between individual activities can be treated as
free slack, thus allowing the activities to be moved
individually in an attempt to level the demand for
resources.
Thank you
Des.
did not explain my problem fully.
I am trying to schedule a project having large necessary
lags between activities.When you set the required lag,you
effectively tie each activity to the chosen lag. Even if
you move one activity, you move them all,because the lag
is not seen to give any free slack to any activity.
In this project there are over 150 activities, so it
seems impossible to level the demand for resources.
My question then is to ask you if there is anyway that
the lag between individual activities can be treated as
free slack, thus allowing the activities to be moved
individually in an attempt to level the demand for
resources.
Thank you
Des.