C
Chris PB
This is a simplified version of my problem:
I have 3 tasks that all take 8 hours and Joe Bloggs and they all start on
the same day (25th October).
Resource Levelling moves tasks 2 & 3 to the 26th and 27th October
respectively.
I want MSP to automatically increase the duration of each task to 3 days and
reduce the resource units to 33% (i.e. have concurrency of tasks).
I have 3 tasks that all take 8 hours and Joe Bloggs and they all start on
the same day (25th October).
Resource Levelling moves tasks 2 & 3 to the 26th and 27th October
respectively.
I want MSP to automatically increase the duration of each task to 3 days and
reduce the resource units to 33% (i.e. have concurrency of tasks).