Resource levelling

A

AMD

I have many sub-tasks assigned to a resource. Some of the tasks overlap and
interfere with other tasks. This results in the resource being assigned to
multiple tasks at the same time. This is indicated by the red font used for
this resource in the resource usage view. I can move the tasks around so
that they do not interfere wtih each other to correct this. The problem is
that there are so many tasks, it would be very tedious to go through each
one. Is there an easy or quick way to have MS Project indicate which tasks
overlap?

Thanks in advance for any help that you can provide.

AMD
 
S

Steve House [MVP]

Take a look at the help topic discussion regarding resource leveling. Be
careful of moving the tasks around manually as in general one should let
Project calculate the task's dates for you instead of inputting them
yourself. Thta's what it's there for.
 