C
CRat
I have an Engineering Drawing Schedule that is linked (externally) to a
Production Schedule. The Design activities compete for a resource called
Designer, of which there are only 20 available, and there are over 300
drawings to do.d
Some of the parts we are designing are different kinds of walls - types A,
B, C, and D. Given that the walls all take the same amount of time to design
and procure, shouldn't Project schedule the ones that are first used in the
production schedule? Wouldn't they have the least lead time (or slack for
that matter)?
I am using leveling order of Priority, Standard (but all are same priority)
and I have checked that Leveling can adjust individual assignments on a task.
Even though type A are used first, I find project scheduleing the design of
C, D, or B first.
Advice Please!
Production Schedule. The Design activities compete for a resource called
Designer, of which there are only 20 available, and there are over 300
drawings to do.d
Some of the parts we are designing are different kinds of walls - types A,
B, C, and D. Given that the walls all take the same amount of time to design
and procure, shouldn't Project schedule the ones that are first used in the
production schedule? Wouldn't they have the least lead time (or slack for
that matter)?
I am using leveling order of Priority, Standard (but all are same priority)
and I have checked that Leveling can adjust individual assignments on a task.
Even though type A are used first, I find project scheduleing the design of
C, D, or B first.
Advice Please!